Monthly Archives: February 2011

Work begins on the roof

Solaris have wasted no time in getting started and neither have they allowed the Great British weather to deter their efforts!  This picture shows the fall safe barrier which is now in place and work is underway to attach rails to the … Continue reading

Posted in Project Updates | Tagged , , | Leave a comment

PV panels arrive

On Monday 14th February the team from Solaris arrived from Germany bringing with them the PV panels.  Over the weekend the remaining propping work to the roof was completed and work can now begin on the exterior of the roof in preparation … Continue reading

Posted in Project Updates | Tagged , | 1 Comment

Weekend work

More activity at church today as another lorry delivered a large load of scaffolding equipment.  DSL will be working all weekend to complete the scaffolding and the essential props and we would like to extend our thanks to team, particularly … Continue reading

Posted in Project Updates | Tagged , , , | Leave a comment

Up in to the heavens

Now I appreciate just how high up the ceiling in the church is!  I was lucky to enough to ascend the scaffolding and saw the work that has been going on over the past week.  Where the ceiling has been … Continue reading

Posted in Project Updates | Tagged , , | Leave a comment

Darkness descends

There must have been a scaffolding frenzy today as when I arrived at 3.15pm inside the church was in darkness and a platform has been erected on the other side of the nave obscuring all light from the windows.  The last … Continue reading

Posted in Project Updates | Tagged , , | 2 Comments