Tag Archives: Reinforcement

At last, the ceiling takes shape!

The team from Fromevale have been working all hours during the last week and great progress has been made.  The structural reinforcement work has now been completed on the 1930s portion of roof as shown above and the insulation has now … Continue reading

Posted in Project Updates | Tagged , , , , | Leave a comment

Keeping the warm in and the cold out!

The week has started with a huge burst of energy and there were 11 contractors on site today working hard on the roof, installing the insulation and even putting in the secondary glazing.  The carpenters are working extremely long, tough hours … Continue reading

Posted in Project Updates | Tagged , , , , | Leave a comment

Yet more timber!

Work has been progressing this week on the roof and on Monday there was a delivery of the formers, shown here, which will provide the barrel shape to the ceiling.  Another load of timber was delivered this morning and it’s … Continue reading

Posted in Project Updates | Tagged , , | Leave a comment

Rocky Road and roof strengthening!

With more carpenters on site work progressed well last week and all unnecessary timbers from the 1930s section of roof have now been removed.  The picture shows a progress meeting between the contractors, architects and members of the PMG whereby the … Continue reading

Posted in Project Updates | Tagged , , , | 2 Comments

Old timbers out, new timbers in!

Hopefully you will have seen the great coverage our project received on BBC South Today news on Sunday evening.  There was a slot at 6.30pm and 10.30pm and the PV panels looked resplendent in the bright sunshine!  This week we … Continue reading

Posted in Project Updates | Tagged , , | Leave a comment